An Coimisiún Pleanála (ACP) has requested further information from Indaver Ireland on its proposed Ringaskiddy incinerator to be submitted by 31 August 2026. View full request. The request follows 991 valid submissions – representing many thousands of people from Cork Harbour and beyond – received during the public consultation period that closed on 17 November 2025. … [Read more...]
Almost 1000 Submissions to ACP – that’s over €49K cost to community!
Almost 1,000 submissions were received to An Coimisiún Pleanala for 17 Nov 2025 deadline for receipt of submissions on the remitted Indaver application, following the 2021 quashing of permission at the High Court. (View Submissions under Third Party submissions) These submissions were accompanied by, or had already paid, the required fee fo 50Euro each, amounting to a total … [Read more...]
! 2016 Planning Application live again – SIGNIFICANT Volume of new information !
Pink area illustrates the areas from which the top of the building will be visible. The stack is visible from even further. Source: Indaver Additional Information Submitted August 2025. View Photomontage file here The January 2016 planning application by Indaver to build a hazardous and non-hazardous waste incinerator at Ringaskiddy, Co Cork, has been reactivated with … [Read more...]
Bord Pleanala Update Letter Brings Incinerator Back into Focus
An update letter issued by An Bord Pleanala, dated 4 June 2024, regarding the reactivated Indaver application has been received by CHASE and Cork Harbour residents who have been battling this application since 2001. This follows the quashing of the 2018 planning grant on March 19, 2021 by High Court Judge David Barniville on the grounds of objective bias by reason of then … [Read more...]
Planning quashed and Judge orders application back to October 2017
High Court Judge David Barniville today delivered his Orders following his Judgement of March 19, 2021 where he found in favour of CHASE on the grounds of objective bias by reason of then Deputy Chairman, Conall Boland’s prior involvement in the application with work done as a consultant on behalf of Indaver in 2004. Having quashed the May 2018 planning granted to Indaver, … [Read more...]