ACP requests current data, proofs to replace claims, and explanations on PFAS and short chimney stack

July 29, 2026 by CHASE

An Coimisiún Pleanála (ACP) has requested further information from Indaver Ireland on its proposed Ringaskiddy incinerator to be submitted by 31 August 2026.  View full request.

The request follows 991 valid submissions – representing many thousands of people from Cork Harbour and beyond – received during the public consultation period that closed on 17 November 2025. Following validation by ACP of these submissions, Indaver submitted a 390-page response on 18 March 2026.  Despite this, the Commission has identified a wide range of issues that persist or have not been addressed.

Key requests include:

  • R1 recovery efficiency – An actual R1 calculation, as Indaver still has not provided the R1 calculation demonstrating that the facility would qualify as a recovery rather than a disposal operation.
  • Noise – Updated baseline surveys using current datasets, rather than relying largely on the 2018 baseline data used in the application.
  • Climate – A full lifecycle climate assessment covering the facility from construction through to decommissioning.
  • Bottom ash – An assessment of the impact that disposal of the plant’s bottom ash could have on Ireland’s landfill capacity.
  • Air quality & the stack – Indaver’s own modelling identifies a Good Engineering Practice stack height of 114.25 metres, while their proposed stack is just 70 metres. ACP has requested Indaver address what this shortfall means for building downwash (i.e. where emissions can be pulled back down towards ground level)  and the resulting pollution concentrations at nearby homes and other sensitive locations.
  • PFAS (“forever chemicals”) – A detailed assessment of how Indaver will monitor and manage PFAS destruction. The European Commission’s Joint Research Centre indicates that temperatures of 1,100–1,200°C are needed to destroy PFAS, significantly higher than Indaver’s proposed operating band of 850–1000°C.
  • Protected habitats – A full cumulative assessment of how the facility’s emissions would affect protected habitats within 15km of the site, including Cork Harbour SPA.
  • Coastal erosion – A revised, site-specific coastal erosion assessment as Indaver has not demonstrated that the site can be protected from future coastal erosion and sea-level rise.

A CHASE spokesperson said:

“We welcome An Coimisiún Pleanála’s decision to seek this extensive further information. The Commission has identified significant areas of real shortcoming.

In plain English, Indaver is being asked to explain how it will make safe chemicals its incinerator can’t reliably operate at a high heat enough to destroy, what a stack 44 metres short of good engineering practice will mean for nearby homes, to update a 10-year-old application with current data and methodology to meet current and future standards across a number of areas, and to prove with calculations instead of reassurances, that this proposed project is not a simple disposal option.

We hope Indaver will be held to the 31 August 2026 timeline, in line with recommendations from the Government’s new Planning and Development Act 2024, which aims to bring timely decision-making to the planning system, and that delay be treated as further evidence for the Commission that this application is not fit to proceed.”

The current reactivated application is a continuation of the 2016 application, planning for which was quashed in the High Court in 2021 on grounds that included objective bias by the then Deputy Chairperson of An Bord Pleanala, and remitted back for reconsideration to ACP.

LINKS:
Letter from ACP to Indaver dated 20 July 2026 requesting Further Information.  View
Indaver Response to submissions – March 2026 View
Further information on 991 Submissions.  Read Article

Share this:

  • Email a link to a friend (Opens in new window) Email
  • Share on X (Opens in new window) X
  • Share on Facebook (Opens in new window) Facebook
  • Share on LinkedIn (Opens in new window) LinkedIn
  • Print (Opens in new window) Print

Filed Under: 2025 Reactivation, An Bord Pleanala, News

Oral Hearing 2016 headlines

  • Serious dioxin figure irregularities exposed as Hearing comes to close
  • No measuring of nanoparticles – not practical, Indaver tell hearing
  • Indaver facility will carry strategic implications for the State – Indaver offer to shut down for Department when needed
  • Indaver to abandon fire fighting after just 2 hours
  • Final Submissions today, questions next week
  • Indaver selective quotation omits that incinerators likely to cause premature deaths
  • 13 year old Cobh student calls for baseline health study for Harbour
  • “There is no risk assessment” – says top Epidemiologist Anthony Staines
  • No safe level of exposure to tiny particulates, says toxico pathologist
  • Royal flush as all TD’s unite to protect the new era for Cork Harbour
  • Ringaskiddy incinerator live plume plot launched
  • Statement from Department of Defence
  • Human Health needs the same standard as protected species: CHASE Opening Statement
  • Indaver experts confirm: High Tide is now inside the site boundary. No separate Health Impact Assessment
  • Packed hearing opens at Carrigaline Court Hotel
  • Full CHASE Submission to An Bord Pleanala

TIMELINE GO FUND ME

 

LIVE PLUME ANIMATION

Live animation of today's plume. (With thanks to Plume Plotter)

TIMELINE

20 years of key dates from when the first planning application was lodged with Cork County Council in November 2001.  VIEW TIMELINE.

ABOUT CHASE

CHASE is an alliance of groups campaigning since 2001 to stop the construction of a large 240,000 tonne commercial incinerator in Cork Harbour. The third application from Indaver Ireland was lodged … Read More...

ORAL HEARING 2016 NEWS

  • Serious dioxin figure irregularities exposed as Hearing comes to close
  • No measuring of nanoparticles – not practical, Indaver tell hearing
  • Indaver facility will carry strategic implications for the State – Indaver offer to shut down for Department when needed
  • Indaver to abandon fire fighting after just 2 hours
  • Final Submissions today, questions next week
  • Indaver selective quotation omits that incinerators likely to cause premature deaths
  • 13 year old Cobh student calls for baseline health study for Harbour
  • “There is no risk assessment” – says top Epidemiologist Anthony Staines
  • No safe level of exposure to tiny particulates, says toxico pathologist
  • Royal flush as all TD’s unite to protect the new era for Cork Harbour
  • Ringaskiddy incinerator live plume plot launched
  • Statement from Department of Defence
  • Human Health needs the same standard as protected species: CHASE Opening Statement
  • Indaver experts confirm: High Tide is now inside the site boundary. No separate Health Impact Assessment
  • Packed hearing opens at Carrigaline Court Hotel
  • Full CHASE Submission to An Bord Pleanala

ORAL HEARING DIARY, from Catriona Reid

A day by day account of the oral hearing experience from Catriona Reid, who was 16 years old at the time and has since published an account in book form. READ DIARY

Read our Privacy Policy here

LINKS

All Press Releases (2001 - Present)
Documents
Privacy Policy

DONATIONS

DONATE ONLINE

Bank Details
AIB Bank, Mainstreet, Carrigaline, Co. Cork
IBAN: IE89 AIBK 9343 1302 5360 94

CONTACT

e-mail: info@chasecorkharbour.com

PRESS ENQUIRIES
Mary O'Leary: 086 8177737
Linda Fitzpatrick: 087 7410849

STAY IN TOUCH

Follow us on twitter or sign up below to get every update straight into your inbox.

It goes without saying your e-mail and details are 100% confidential and will never be shared with anyone or used for any purpose other than CHASE updates.

SUBMIT an event or SEE all events this month

Tweets by @CHASECorkNews

UPCOMING MEETINGS & EVENTS


PUBLIC MEETING: TUESDAY OCTOBER 21st.  2 Point Road Crosshaven.  7.30pm (Cafe beside Cronin’s Pub)

PUBLIC MEETING:  THURSDAY NOVEMBER 6th.  Ringaskiddy Community Centre.

© 2026 · CHASE · Cork Harbour Alliance for a Safe Environment · Commercial permission reserved